Cleanrooms for the Vitaluce Pharmacy

Hochdorf

The Vitaluce Pharmacy AG needed new cleanrooms in an existing listed building. The cleanrooms are used for processing dermatological hormone products, human-identical hormones and micronutrients from the online pharmacy.

"[For the Willers project team] the problem was never the focus, but rather the search for the optimal solution. I appreciated that very much during the course of the entire project". 
Jeannine Kohl
Managing Director of Toppharm Apotheke Hochdorf

"[For the Willers project team] the problem was never the focus, but rather the search for the optimal solution. I appreciated that very much during the course of the entire project". 
Jeannine Kohl
Managing Director of Toppharm Apotheke Hochdorf

How do we build GMP-compliant cleanrooms in a listed building?

Challenges
 The old building presented us with some challenges. There were no riser shafts, the load-bearing capacity of the ceilings was too low so that the mono-blocks could not be hanged onto the ceiling. Besides, the statics of the floor were not sufficient: the load-bearing capacity was only 250 kg/m2 (normal capacity is about 1000 kg/m2). The capsule machine alone already weighs 1000 kg/m2.

In addition, bringing in the components was a challenge because the doors were small and there was no goods lift.

Cleanroom implemented as a "room-in-a-room" concept.

Solutions
Due to the circumstances at hand, we decided on a room-in-a-room layout. In this way, the cleanrooms were detached from the outer façade. In this way, we created a controllable intermediate zone that could be used as a technical zone. This meant that we hardly had to touch the outer façade, but could use it to support the weight of the technical components. The windows could still be opened and the existing heating could be used.

In addition, we decided to use recirculation. Each zone with a product or a processing step was equipped with its own recirculation unit. These zones are supplied with air from a central fresh air system (attic). This allowed us to use an existing cabinet niche as a riser zone and smaller air outlets were thus created on the roof in keeping with the preservation of historical monuments. In addition, we were able to save approx. 75% energy due to the greatly reduced heating, cooling, humidification and dehumidification requirements of the system.
Cleanroom
General Planning
Lab
Cleanroom
Lab
General Planning

Cleanroom Systems

Magnus Willers

CEO

Magnus Willers

CEO
People Solutions Technology People Solutions Technology 员工 解决方案 技术